Our Gadsden development is making exceptional progress with the project still on track to reach completion in early 2023.
- Basement retention, excavation & piling works are now complete
- Slab on Ground is nearing completion
- B1 pour 1 complete with formwork progressing from west to east of the site
- Tower cranes erected and operational
- In-ground services ongoing
Over the next few months, we will see the erection of the concrete structure with high-level services to follow.