Our Gadsden development is making exceptional progress with the project still on track to reach completion in early 2023.
– Basement retention, excavation & piling works are now complete
– Slab on Ground is nearing completion
– B1 pour 1 complete with formwork progressing from west to east of the site
– Tower cranes erected and operational
– In-ground services ongoing
Over the next few months, we will see the erection of the concrete structure with high-level services to follow.
PDG is Melbourne’s most successful and trusted commercial building developer.