Both stages of the Munro development are steadily tracking towards completion.
Stage 1
Works are progressing well at the City of Melbourne’s largest new community hub, with the façade windows now nearing completion. PDG successfully handed over the 4-level basement carpark in March 2021, where fit-out works are being completed prior to it being operational later in the year.
Completion of the hub is scheduled for September 2021.
Stage 2
On the tower side, the lift core is now up to Level 16, with the slabs at Level 10. Façade works have commenced on Level 6 and hotel room fit-out works are underway for Levels 1-3.
The hotel, retail and Mirvac’s Build to Rent offering are expected to be completed in October 2022.
The Munro development is one of PDG’s most exciting and important mixed-use projects to date. We look forward to sharing more milestones as we approach completion and handover.